agile agile architecture AYE conference Behind Closed Doors capacity change collaboration conference context estimation feedback geographically distributed teams inch pebble iterative planning kanban leadership lean lifecycle Manage It management management myth Manage Your Project Portfolio meetings multitasking one-on-one pairing Pragmatic Manager product development productivity program management project project management project portfolio project portfolio management project success project team release criteria risk team technical debt testing timebox transition to agile transparency workshop
Tag Archives: estimation
What You Can Do For Estimation
In But I Need to Know When the Project Will Be Done, I talked about what you can do for estimating an agile project (do a gross estimate of the backlog, estimate your velocity, better your estimate every iteration and … Continue reading
How Short Can Your Program Charters Be?
A great way to destroy a program is to avoid writing a charter. When I do assessments or work with teams, I often find that programs do not have charters, or that the charter is too big, or is missing … Continue reading
Posted in agile
Tagged estimation, product development, program management, project management
1 Comment
Estimation Depends On…
I taught my estimation workshop twice last week and once the week before, and one thing remains true: Estimation depends on the project lifecycle, how the project is organized, the state of the requirements, and the number of people you … Continue reading
Estimation Units Predict Schedule Slippage
I’ve been teaching a project management workshop, and one of the participants said something brilliant: “If you estimate in days, you’ll be off by days. If you estimate in weeks, you’ll be off by weeks.” If you estimate in months, … Continue reading
Estimating Tasks: How Much Time is in Your Day?
I plan on about 6 hours of work in a regular day. That’s project work, not answering the phone, email, making arrangements for workshops or consulting or speaking, or invoicing, or any of the other things I do. Nope, … Continue reading
Estimating What’s Remaining to Finish
Pawel caught me being ambiguous. See his comment, “1. I’ve seen features/fixes which required 2 days to be developed and released.” Sorry, me too. But what I tried to say was this: A feature was estimated to be some … Continue reading
Probabilistic Scheduling
I’m writing my project management book. I have no idea how far along I am. (Wait, I promise to explain.) When I write, I have several phases: the exploratory phase, where I write articles, the write-it-down phase, where I … Continue reading
Need Help with a Phrase
I’m writing the project management book. I’m noting that sometimes PMs (and teams) perform activities that have no lasting useful effect on the project. One example is doing estimation with feedback. If you estimate but never check reality against … Continue reading