Milestones and Handoffs

  James’ comment and Eric’s comment asked good questions about why I differentiate between milestones and handoffs. Milestones can be a collection of events (handoffs) that culminate in one milestone. Let’s take the milestone “code freeze” or “code complete.” The code doesn’t magically all become complete on one day; some of the code is completed […]

MPD, schedule

Handoffs: The Reasons Behind Interim Milestones in Schedules

  In the last couple of years, I’ve worked with some project managers who thought the reason they made schedules was to know when the milestones would be met. They thought if they knew when “design complete” or “feature freeze” or “code complete” occurred, they could track the schedule. I’ve never been comfortable with that,

MPD

Optimization and Capacity, Reprise

  Oh dear. I was not sufficiently articulate in my last post. Both Frank and David in their comments asked about capacity, the output of the organization over time. That will teach me to post when I’m tired. (Maybe.) Let me try this again. In each of these projects, senior management wanted more features than

Scroll to Top